| Should be in the package | Should NOT be missing | What happens if it's missing |
| :-- | :-- | :-- |
| Quantity takeoff by scope (clearing, earthwork, utilities, drainage, paving) | Assumptions behind the takeoff (soil conditions, haul distances, disposal) | Quantities get disputed mid-job, usually as a change order |
| Explicit exclusions list | Vague catch-all language like "per plans and specs" | GC assumes something is included that the sub never priced |
| Utility conflict and locate assumptions | Unresolved plan conflicts | RFIs pile up after mobilization instead of before |
| Erosion control and drainage scope | Florida-specific rain and soil assumptions | Stormwater compliance becomes a field-level scramble |
| Sequencing notes tying phases together | A single lump-sum line with no phase breakdown | GC can't tell if the schedule is realistic |
Foshee recently broke ground on Plant Street, a commercial project in Winter Garden, and is beginning construction on Alahambra, a medical office project in Lake Mary. Both jobs moved from bid to mobilization without the kind of scope surprises that stall a schedule in its first weeks — because the bid packages spelled out quantities, exclusions, and utility sequencing clearly enough for the GC to build from at award, not renegotiate after breaking ground.

An exclusions list that's short or vague. If a bid doesn't say clearly what's not included, assume there's a gap that will surface as a change order once the crew is in the field.
A phase breakdown is worth insisting on. It lets a GC see whether clearing, earthwork, utilities, and paving quantities were actually estimated separately or bundled together to hide a weak spot.
Through HeavyBid and AGTEK, which sharpen quantities and scope assumptions before the number ever reaches the GC — reducing the odds that a takeoff was eyeballed rather than modeled.
Ask before award, not after. Every clarification resolved at the bid stage is a change order that never has to happen during construction.
A complete bid package isn't a formality — it's the document a GC will actually build the schedule around. Quantities, exclusions, and sequencing that are clear at award are the difference between a job that runs on the numbers it was priced at and one that spends its first month renegotiating them, the way Plant Street and Alahambra were able to move straight from award into active construction.
Foshee Construction builds sitework bid packages GCs can build from. To discuss a project, start with the Foshee contact page - https://fosheeconstruction.com/contact.
- Why Self-Performed Sitework Gives Developers More Control - https://fosheeconstruction.com/blog/self-performed-sitework-developer-control
- Construction Safety Audit Guide - https://fosheeconstruction.com/blog/construction-safety-audit
- Utility Installation - https://fosheeconstruction.com/blog/utility-installation
- 811 Utility Locates - https://fosheeconstruction.com/blog/811-utility-locates
- Foshee Projects - https://fosheeconstruction.com/projects
We build bids using HeavyBid and AGTEK because the details matter long before the job starts. When the numbers are accurate and the scope is clearly defined, it sets the tone for how the entire project runs. Estimating isn’t just a step in the process, it’s the foundation we build on.
That same mindset carries into the field. Our crew is trained to work with purpose, follow the Civil Engineers’ Plan to the finest detail, and hold the line on quality. When expectations are clear from day one, there’s no need for shortcuts, and no confusion about how the work gets done.
Clients trust our bid packages because they’re complete and ready to use. Project managers know what we’re covering, what’s excluded, and how we plan to approach the job. That clarity removes friction and lets teams focus on execution instead of interpretation.
As part of our review process, we go into the plans before anything hits the site. We ask the questions early, resolve issues before they show up in the field, and keep RFIs moving. This approach prevents delays and protects the timeline.
Over time, that consistency builds trust. Many of the people we work with today came through referrals from past projects – engineers, GCs, and superintendents who’ve seen how we operate and want the same experience again.

In 2024, Foshee Construction was acquired by Saga Infrastructure Solutions, a national network of civil construction companies. Saga supports regional contractors by giving them access to better tools, long-term resources, and operational backing, without changing how they run day to day.
Foshee will continue to operate under its name, with the same team and field leadership in place.
“From the very time a project starts, we start that partnership. We try to catch as much as we can with the tools that we have. Not everybody is using the software platforms we are. That’s the differentiator: we’re not just bidding. We’re anticipating, problem-solving, and making sure the job runs right.”
— Don, CEO, Saga Infrastructure Solutions
Foshee is now part of a broader regional strategy that includes Florida, the Piedmont Atlantic, Texas, Colorado, and the Arizona Sun Corridor. The name, crews, and standards remain. What’s improving is the support behind it.